Nornickel’s development strategy



Growing mining production volumes, upgrading processing facilities, and maintaining market positions
Norilsk site

Kola site
Infrastructure
-
Increased throughput capacity of the Dudinka port and the Company’s own terminal in Murmansk -
Renovation of generation capacities -
Comprehensive reduction of energy losses
Trans‑Baikal Division
Production volumes for 2024
| | |
| |
2025 forecast:
| 66-70 |
Production volumes for the Group Excluding the Trans‑Baikal Division.
| | | |
|---|---|---|
| | 204-211 | |
| | 353-373 | |
| 2762 | 2704-2756 | |
| | 662-675 |
South Cluster: growing production volumes

-
In 2024, a positive opinion was obtained from Glavgosexpertiza following the re‑examination of the design and cost estimate documentation. Subsequently, the development of optimisation measures for mine construction commenced. -
Mine development and construction works are ongoing for the underground mine and related infrastructure facilities. -
In 2025–2026, the Company intends to secure positive opinions from Glavgosexpertiza as well as a certificate of compliance for the mine and related infrastructure construction project.
2028 production targets
| | |
| 750-850 | |
| 13+ | |
| 20+ |

Upgrade of Talnakh Concentrator: the third start‑up facility
Project status
-
In 2024, the design documentation was adjusted, and the execution of supply contracts for flotation and thickening equipment was completed. -
Tendering is currently underway for ore dressing units and ore feeders, covering a range of activities to complete construction and installation, including the installation of metal frames and fences. -
Installation of foundations for the blower and reactor process equipment is currently underway. -
In 2025, the Company plans to secure a positive opinion from the Main Department of State Expertise (Glavgosexpertiza) on the amended design documentation.
Projected implementation timeline
Upgrade of flash smelting furnaces at Nadezhda Metallurgical Plant (NMP)
-
In 2024, NMP completed an overhaul of FSF No. 2, a unique project comparable in scale and effort to constructing a new furnace. -
Despite the logistical challenges and constraints caused the disruption of equipment supplies from foreign vendors, the project was completed in less than 60 days . -
The project resulted in a 25 % increase in the furnace’s capacity for concentrate processing. -
The Company is currently developing a set of measures to upgrade FSF No. 1 with a waste heat recovery boiler, planned for implementation in 2027. -
The FSF No. 1 upgrade also includes production capacity expansion at NMP.
The Trans‑Baikal Division’s mining and processing plant



-
In 2024, the first projects under the long‑term efficiency and capacity expansion strategy came online: magnetic separation capacity additions and a gold concentrate dehydration unit. The development of main technical solutions was also completed, and the preparation of detailed design documentation commenced for the gold mill project. -
In 2025, projects to upgrade the gri nding circuit, flotation section, and thickening section of the concentrator are scheduled for commissioning. Plans are also in place to commence construction of a gold mill.
Production volumes
| | | |
|---|---|---|
| | | |
| | | 66-70 |
| | | 2,75-2,85 |
Mining capacity expansion at Severny Mine
Site overview
-
Severny underground mine -
Zapolyarny Concentrator -
Concentrate shipment section -
Auxiliary infrastructure facilities
Mineral resource base
| | | |
|---|---|---|
| | | |
| 2796 | | |
| 1376 | |
Infrastructure expansion and upgrades
Logistics Infrastructure Development Programme
Programme rationale
-
Increased volumes of westward shipments of semi‑products once the copper production chain reconfiguration programme is completed. -
Adjusted pace of fixed asset replacement in the Norilsk Industrial District, reflecting the optimisation of the investment programme. -
Expansion of Northern Sea Route operations and increased freight volumes for major investment projects of other companies using the NSR in the Russian Arctic.

Energy infrastructure upgrade programme
Gas and gas condensate exploration, production, and transportation
-
In 2024, a retrofitting project was completed for a gas pipeline’s underwater crossing of the Bolshaya Kheta River. -
Drilling operations continue on five wells at well pad No. 4 of the Pelyatkinskoye gas condensate field, expected to come online in 2025. -
Pre‑commissioning operations are underway at the booster compressor station of the Severo‑Soleninskoye gas condensate field, with commissioning planned for 2025.
NGV fuel
Combined heat and power plants
-
In 2024, construction and installation activities were completed for the revamp of Unit No. 2 of CHPP‑2, with pre‑commissioning operations ongoing and commissioning scheduled for 2025. -
The tank farm revamp programme continues, with five new tanks constructed since its start: -
2 tanks at CHPP‑1 -
2 tanks at CHPP‑2 -
1 tank at CHPP‑3
-
Energy infrastructure
Sulphur Project at Nadezhda Metallurgical Plant

